Detalles del Proyecto
Ubicación: Changi International Airport
Singapore
Proyecto: Development at Former South End Reservoir Site
Contratista: Hock Lian Seng Group
Dueño: CAG
DesafÃos:
- Multi-phased project required careful coordination with main contractor
- Tight conformance to applicable regulations
- Very short lead-time to perform the design and delivery
BDI supplied both the G14NB-6 (4.2m/14′ tall) and G20NB-6 (6m/20′ tall) for this project. All material was powder coated after being hot-dip galvanized, for improved aesthetics and corrosion resistance. BDI deflectors have been in use at Changi for more than 30 years.